1. 则此类延误或干扰应被视为是属于第8.4款段中规定的一种延误原因。
Then this delay or disruption will be considered as a cause of delay under sub-paragraph of Sub-Clause 8.4 (Extension of Time for Completion).
2. 在此支付表中所报的分期支付额即为第14.3款段所述的合同价值
A the instalments quoted in this schedule of payments shall be the estimated contract values for the purposes of sub-paragraph of Sub-Clause 14.3
3. 在此支付表中所报的分期支付额即为第14.3款段所述的合同价值
A the instalments quoted in this schedule of payments shall be the estimated contract value s for the purposes of sub-paragraph of Sub-Clause 14.3
4. 如果第17.3款段及段的情况发生,上述费用应加上合理的利润。
In the case of sub-paragraphs and of Sub-Clause 17.3, reasonable profit on the Cost shall also be included.